A Discussion Of "Close-Out" Management In The Big International EPC Contract
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    合同关闭管理是合同精细化管理的要求,该环节往往被我国的承包商所忽视,是合同管理过程中的薄弱环节。国际EPC合同关闭期间主要有机械完工、临时接收和最终接收三个节点。为了避免关闭过程中的不确定性,应遵循一定的合同关闭原则。为防止出现漏项,应按照关闭检查清单逐一排除。EPC关闭合同有十个方面的内容需要承包商高度注意。承包商应制定合同关闭管理程序。

    Abstract:

    Contract closed management is the requirements of fine management which the link is often ignored by the Chinese contractor, is also the weak link in the process of contract management. Closure of international EPC contract mainly includes Mechanical Completion and Provisional Acceptance as well as Final Acceptance. In order to avoid the uncertainty in the process of closing, certain principles of contract closure should be followed. To prevent leakage, items should be ruled out one by one according to closing checklist. Ten parts of the Close-out contract are needed high attention by the contractor. The contractor shall formulate contract Close -out management procedure.

    参考文献
    相似文献
    引证文献
引用本文

张浩.国际大型EPC合同的“关闭”管理[J].,2014,(23).

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2014-07-02
  • 最后修改日期:2014-11-13
  • 录用日期:2014-09-02
  • 在线发布日期: 2014-12-12
  • 出版日期:
文章二维码

联系电话:020-37635126(一、三、五)/83568469(二、四)(查稿)、37674300/82648174(编校)、37635521/82640284(财务)、83549092(传真)

联系地址:广东省广州市先烈中路100号大院60栋3楼302室(510070) 广东省广州市越秀区东风西路207-213星河亚洲金融中心A座8楼(510033)

邮箱:kjgl83568469@126.com kjgl@chinajournal.net.cn

科技管理研究 ® 2025 版权所有
技术支持:北京勤云科技发展有限公司
关闭
关闭