项目群工期目标是南水北调工程项目群目标之一,如何花费最低达到合同约定的项目群工期目标已成为南水北调工程项目群优化的主要问题之一。本文从业主视角出发,通过对费用最低的项目群工期优化机理的分析,利用压缩关键线路上的项目或者同时压缩关键线路、非关键线路上项目的方法,分析了压缩项目群工期对项目本身、关键线路、非关键线路上项目的影响,并考虑了业主因项目群工期压缩而获得的收益,据此构建了基于费用最低的项目群工期优化模型。结合南水北调中线京石段应急供水工程第六标项目群的工期优化,对模型进行了实证分析。本文的研究成果为业主科学地进行大型工程项目群工期优化提供了参考。
[Key word]
[Abstract]
Progress goal is one of the objectives of South-to-North Water Diversion Project programme, how to spend the lowest cost to achieve the programme’s objectives required by the contract period the group has become the owners of large engineering decisions difficult. From the owner perspective,by analyzing the lowest group of the project duration optimization mechanism,the use of compression on the critical path of the project or while compressing the critical path,the method of non-critical items on the line,analyzes the compression Programme duration of the project itself the key line, non-critical line on the impact of the project and to consider the benefits due to the project owners group obtained compressed schedule. Accordingly optimization model was constructed based on the cost of the minimum duration of the project group,combined with the sixth bid section of South-to-North Water Diversion Jingshi emergency water supply project Programme was empirical analysis. Results of this study for the owners to scientific and reasonable to carry out large-scale projects swarm optimization provides a reference period.
[中图分类号]
[基金项目]
【1】基础设施领域财政支持公私合作伙伴(PPP)机制创新,2014年度国家社科基金重点项目(14AZD024);【2】中国博士后基金:重大水利工程项目组织协同演化及治理机制研究,中国博士后科学基金(2014M551498);【3】大型基础设施财政支持公私合作伙伴(PPP)项目决策机制研究,中央高校基本科研业务费专项资金资助(2014B09014);【4】教育部创新团队(IRT13062),国际河流战略与情报监测研究,2014年。